Maximum Demand Calculator

Calculate whole-building maximum demand for DNO supply applications, main fuse sizing, and ADMD for multi-dwelling developments according to BS 7671

Whole-Building Maximum Demand Assessment

Calculate the maximum demand for an entire building or development for DNO supply applications and main fuse/cable sizing. This tool applies BS 7671 diversity factors at the whole-building level and includes ADMD calculations for multi-dwelling developments.

Select the type of building or development for appropriate diversity calculation

Building Loads

kW

Power rating per unit

Number of identical loads

Existing Supply (Optional)

A

Enter 0 or leave blank for new installations

Typical Load Values (for reference)
Heating & Hot Water
  • • Electric shower (9.5kW): 41.3A
  • • Immersion heater (3kW): 13.0A
  • • Storage heater (3.4kW): 14.8A
  • • Heat pump ASHP (6-12kW): 26-52A
  • • Panel heater (2kW): 8.7A
Cooking & Appliances
  • • Electric cooker (11kW): 47.8A
  • • Induction hob (7.4kW): 32.2A
  • • Electric oven (3kW): 13.0A
  • • Washing machine: 10A
  • • Socket circuit (ring): 32A rated
EV & Renewables
  • • EV charger 7.4kW: 32A
  • • EV charger 22kW (3ph): 32A/phase
  • • Lighting circuit: ~2A typical
  • • LED lighting (whole house): 0.5-1.0kW

Single-phase: Amps = kW x 1000 / 230V. Three-phase: Amps = kW x 1000 / (400V x 1.732).

What is Maximum Demand?

Maximum demand is the highest rate of electrical energy consumption that an installation or building is expected to draw at any point in time. It is a critical value required by BS 7671 Regulation 311.1 for the design of every electrical installation. Unlike the total connected load (the sum of all equipment ratings), maximum demand accounts for the statistical improbability that all electrical equipment will operate at full capacity simultaneously.

Accurate maximum demand assessment is essential for selecting appropriate protective devices, sizing supply cables and main switches, and determining the capacity of the electricity supply from the Distribution Network Operator (DNO). Every Electrical Installation Certificate (EIC) must include a justified maximum demand figure -- it should never simply be copied from the service cut-out fuse rating.

Connected Load

The sum total of all equipment ratings if every load operated at maximum capacity simultaneously. This is always higher than maximum demand.

Maximum Demand

The realistic peak load after applying diversity factors. This is the value used for sizing supplies, cables, and protective devices.

Diversity Factor

The ratio of maximum demand to connected load (always less than 1.0). Reflects that not all loads operate simultaneously.

ADMD Explained: After Diversity Maximum Demand

ADMD (After Diversity Maximum Demand) is the key metric used by Distribution Network Operators (DNOs) when assessing supply requirements for multi-dwelling developments such as housing estates, apartment blocks, and mixed-use schemes.

The ADMD per dwelling decreases as the number of units increases. This is because with more dwellings, the statistical probability of all occupants using maximum power simultaneously becomes negligible. A single dwelling might have a peak demand of 15-20 kW, but the ADMD allocated per dwelling in a 100-unit development may be only 1.5-4 kVA depending on heating type.

Typical ADMD Values

Gas-Heated Dwellings

  • • Standard: 1.5 - 2.0 kVA per dwelling
  • • With EV charging: 3.0 - 4.0 kVA per dwelling

All-Electric Dwellings

  • • Storage heating: 3.0 - 3.5 kVA per dwelling
  • • Heat pump: 4.0 - 6.0 kVA per dwelling

ADMD values are guided by ENA Engineering Recommendation P2/7 and are subject to regional variation. Always confirm values with your local DNO.

DNO Supply Applications

When the calculated maximum demand exceeds the existing supply capacity, or for all new developments, an application must be made to the Distribution Network Operator (DNO). In London, this is typically UK Power Networks (UKPN). The application must include an accurate maximum demand assessment.

Single-Phase Supply Limits

  • 60A -- Older domestic standard. Max ~13.8 kVA. Often inadequate for modern homes with EV charging.
  • 80A -- Current standard for new domestic installations. Max ~18.4 kVA.
  • 100A -- Maximum single-phase supply available. Max ~23 kVA. Required for large homes with electric heating and EV charging.

Three-Phase Supply

  • 63A/phase -- Capacity ~43.6 kVA. Suitable for large homes with multiple high-load appliances.
  • 80A/phase -- Capacity ~55.4 kVA. Average upgrade cost: ~£5,000.
  • 100A/phase -- Capacity ~69.3 kVA. Above this, CT metering is required.

When DNO Notification is Required

  • EV Charging: All EV charge point installations require DNO notification (BS 7671 states no diversity for individual EVCPs)
  • Heat Pumps: Installations that increase demand beyond the existing supply fuse rating
  • Supply Upgrades: When calculated maximum demand exceeds the current service fuse rating (60A, 80A, or 100A)
  • New Developments: All new builds and conversions require a new supply application
  • Additional Meters: Any property requiring additional metering or CT metering

BS 7671 Table 1A Diversity Factors (Domestic Dwellings)

These diversity factors from the IET On-Site Guide Appendix A are applied at the whole-building level to determine maximum demand. They differ from circuit-level diversity applied to individual final circuits.

Circuit TypeDiversity Allowance
Lighting66% of total current demand
Heating & Power100% up to 10A + 50% of remainder
Cooking Appliances10A + 30% of full load remainder + 5A if socket on cooker control
Instantaneous Water Heaters100% of largest + 100% of second + 25% of remainder
Thermostatic Water Heaters100% of full load (no diversity)
Floor Warming / Storage Heaters100% of full load (no diversity)
Socket Outlets100% of largest circuit + 40% of every other circuit
EV Charge Points100% -- no diversity (BS 7671 requirement)
Heat Pumps100% -- continuous load, no diversity

Note: Diversity should only be applied by competent persons with relevant knowledge and experience. These factors are guidance values from the IET On-Site Guide -- actual usage patterns should be considered.

Worked Example: 3-Bed Semi-Detached House

A typical domestic maximum demand calculation for a 3-bedroom semi with gas central heating, electric cooker, and electric shower.

CircuitConnected LoadDiversity RuleDemand (A)
Lighting (3 circuits)~15A total66%9.9A
Ring final 1 (kitchen)32A100% of largest32.0A
Ring final 2 (downstairs)32A40% of others12.8A
Ring final 3 (upstairs)32A40% of others12.8A
Cooker (12kW)52.2A10A + 30% + 5A (socket)27.7A
Shower (9.5kW)41.3A100% (instantaneous heater)41.3A
Immersion heater (3kW)13A100% (thermostatic)13.0A
Total Maximum Demand149.5A → ~80A service fuse

Wait — 149.5A on an 80A fuse? This is the theoretical maximum if every circuit hits peak simultaneously. In practice, the shower and cooker rarely run at full load together, and socket diversity further reduces actual peak. An 80A supply is considered adequate for this installation. If an EV charger (32A) is added, the demand exceeds 80A and a supply upgrade or load management device is required.

Common Maximum Demand Questions

What is maximum demand on an EIC?

Box 311.1 on the Electrical Installation Certificate requires the assessed maximum demand of the installation. This should be the calculated demand after applying diversity factors — not the main fuse rating. Many electricians incorrectly enter “80A” or “100A” (the service fuse). The correct entry is the diversified maximum demand you calculated (e.g., “65A”). NICEIC and NAPIT inspectors check this field during audits.

How do I know if I need a supply upgrade?

Calculate the maximum demand including the new load (EV charger, heat pump, etc.). If it exceeds your main fuse rating (check the fuse at the meter — typically 60A, 80A, or 100A), you need either a supply upgrade from the DNO (typically £500-2,000 for fuse upgrade, more if new cable needed) or a load management device that curtails lower-priority loads (e.g., pausing the EV charger when the shower is running).

Can I apply diversity to an EV charger?

No. BS 7671 states that EV charge points should be taken at 100% of their rated current with no diversity applied for individual installations. A 7.4kW (32A) EVCP adds 32A to your maximum demand calculation. For multi-dwelling developments, the DNO may apply ADMD diversity across multiple charge points using smart charging profiles, but the individual installer must assess at full load.

What is the difference between maximum demand and ADMD?

Maximum demand is the peak load for a single installation. ADMD (After Diversity Maximum Demand) is the average peak demand per dwelling in a multi-dwelling development, accounting for the statistical diversity between households. ADMD decreases as the number of dwellings increases (e.g., 2.0 kVA per dwelling for 100 gas-heated flats vs 8-15 kVA for a single house).

Do I need to notify the DNO when adding a cooker or shower?

Not usually, provided the new circuit doesn't push the total maximum demand above the existing service fuse rating. However, if the property already has a high-power shower, EV charger, and you're adding a 15kW range cooker, recalculate the total demand. If it exceeds the main fuse, you need a DNO application for a fuse upgrade before energising the new circuit.

Standards & References

  • • BS 7671:2018+A2:2022 Regulation 311.1 -- Assessment of general characteristics (Maximum demand)
  • • IET On-Site Guide Appendix A -- Maximum demand and diversity (Tables A1 and A2)
  • • IET Guidance Note 1: Selection & Erection -- Chapter 3 (Assessment of general characteristics)
  • • ENA Engineering Recommendation P2/7 -- Planning limits for voltage fluctuations and ADMD
  • • BS EN 61439-3 -- Rated Diversity Factor (RDF) for assemblies
  • • Building Regulations Part S -- Infrastructure for the charging of electric vehicles
  • • Building Regulations Part L 2021 -- Conservation of fuel and power (impacts electrification of heat)
  • • NAPIT & NICEIC -- EIC documentation requirements for maximum demand recording

Was this calculation helpful?