Voltage Drop Calculator - BS 7671 Compliant

Calculate voltage drop and check BS 7671 compliance for electrical installations

Calculate Voltage Drop

Check if your cable installation meets BS 7671 voltage drop requirements

Amps

The current flowing through the cable

meters

One-way cable run distance

Cross-sectional area of the conductor

How to Calculate Voltage Drop UK - Complete Guide

Voltage drop calculation is essential for ensuring electrical installations comply with BS 7671 regulations. This guide explains the complete process for UK electrical systems.

Step 1: Understand BS 7671 Voltage Drop Limits

BS 7671 Regulation 525 specifies maximum voltage drop limits:

  • Lighting circuits: Maximum 3% of nominal voltage (230V × 3% = 6.9V maximum drop)
  • Other circuits: Maximum 5% of nominal voltage (230V × 5% = 11.5V maximum drop)
  • Three-phase systems: Measured line-to-line (400V system)

Step 2: Identify the Required Values

To calculate voltage drop, you need:

  • Cable length (L): One-way distance in meters from source to load
  • Design current (Ib): Maximum current the circuit will carry in Amps
  • Cable size: Cross-sectional area in mm²
  • mV/A/m value: From BS 7671 voltage drop tables (Table 4D5, 4E4A, etc.)
  • Phase type: Single-phase (230V) or three-phase (400V)

Step 3: Use the Voltage Drop Formula

The formula differs between single-phase and three-phase systems:

Single-Phase Formula:

Voltage Drop (V) = (mV/A/m × Length × Current) ÷ 1000

For 230V single-phase circuits (most domestic installations)

Three-Phase Formula:

Voltage Drop (V) = (mV/A/m × Length × Current × √3) ÷ 1000

For 400V three-phase circuits (commercial/industrial)

Then convert to percentage: (Voltage Drop ÷ Nominal Voltage) × 100

Step 4: Find mV/A/m Values from BS 7671 Tables

The millivolt drop per amp per meter (mV/A/m) is found in BS 7671 tables:

  • Table 4D5: Twin & earth cables (PVC insulated)
  • Table 4E4A: Single-core cables in conduit
  • Table 4D4A: SWA armoured cables
  • Table 4J4A: Mineral insulated cables

These values account for both conductor resistance and reactance at operating temperature. For the complete tables, see the BS 7671 voltage drop reference tables.

Important: BS 7671 itself does not publish the voltage drop formula — it only publishes the mV/A/m values. The formula Vd = (mV/A/m × L × I) ÷ 1000 is derived from Ohm's law (V = IR), with mV/A/m representing the complex impedance (resistance + reactance) per metre. UK trade practice for domestic work commonly skips temperature correction and uses tabulated values directly as a conservative worst-case.

Real-World Example: 32A Shower Circuit

Given: 32A shower, 15m cable run, 6mm² twin & earth, 230V

Step 1: From Table 4D5, 6mm² cable = 7.3 mV/A/m

Step 2: Calculate voltage drop:

Vd = (7.3 × 15 × 32) ÷ 1000 = 3.504V

Step 3: Convert to percentage:

(3.504 ÷ 230) × 100 = 1.52%

✓ Result: 1.52% is under the 5% limit - compliant with BS 7671

Common Mistakes to Avoid

  • Using cable length as return distance - always use one-way length
  • Forgetting to divide by 1000 (mV to V conversion)
  • Using incorrect mV/A/m values for the cable type
  • Not accounting for the √3 factor in three-phase calculations
  • Checking only current capacity and forgetting voltage drop

Voltage Drop Tables UK - mV/A/m Values BS 7671

Quick reference voltage drop values (mV/A/m) from BS 7671 for common UK cable types. These values are used in voltage drop calculations.

Twin & Earth Cable (6242Y) - Voltage Drop Values

Cable SizemV/A/mExample: 10m @ 20AMax Length @ 5%
1.0mm²44 mV/A/m8.8V (3.8%)26m @ 20A
1.5mm²29 mV/A/m5.8V (2.5%)40m @ 20A
2.5mm²18 mV/A/m3.6V (1.6%)64m @ 20A
4.0mm²11 mV/A/m2.2V (1.0%)52m @ 32A
6.0mm²7.3 mV/A/m1.46V (0.6%)79m @ 32A
10.0mm²4.4 mV/A/m0.88V (0.4%)87m @ 40A

Reference: BS 7671 Table 4D5 (2-core cables with protective conductor, 70°C thermoplastic)

SWA Cable - Voltage Drop Values

Cable SizemV/A/m (2-core)mV/A/m (3-core)Typical Use
2.5mm²18 mV/A/m18 mV/A/mGarden lighting
4.0mm²11 mV/A/m11 mV/A/mGarage sub-mains
6.0mm²7.3 mV/A/m7.3 mV/A/mEV chargers, outbuildings
10.0mm²4.4 mV/A/m4.4 mV/A/mLarge outbuildings
16.0mm²2.8 mV/A/m2.8 mV/A/mCommercial sub-mains

Reference: BS 7671 Table 4D4A (Armoured 70°C thermoplastic cables)

💡 Quick Tip: Lower mV/A/m values mean less voltage drop. For long cable runs, use larger cable sizes to reduce voltage drop and stay within BS 7671 limits.

Voltage Drop Calculation Examples - Step by Step

Follow these worked examples to understand voltage drop calculations for common UK installations.

132A Ring Main Circuit - 2.5mm² Cable

Scenario:

  • Circuit: 32A socket ring main
  • Cable: 2.5mm² twin & earth
  • Length: 28m (one leg of ring)
  • Load: 20A (typical maximum on one leg)

Calculation:

mV/A/m for 2.5mm² = 18 mV/A/m (Table 4D5)

Vd = (18 × 28 × 20) ÷ 1000 = 10.08V

Percentage = (10.08 ÷ 230) × 100 = 4.38%

✓ Result: 4.38% - Within 5% limit for power circuits

2Lighting Circuit - Checking 3% Limit

Scenario:

  • Circuit: 6A lighting circuit
  • Cable: 1.5mm² twin & earth
  • Length: 35m to furthest light
  • Load: 5A (LED lighting)

Calculation:

mV/A/m for 1.5mm² = 29 mV/A/m (Table 4D5)

Vd = (29 × 35 × 5) ÷ 1000 = 5.075V

Percentage = (5.075 ÷ 230) × 100 = 2.21%

✓ Result: 2.21% - Within 3% limit for lighting

3EV Charger Long Run - Voltage Drop Exceeds Limit

Scenario:

  • Circuit: 32A EV charger (7.4kW)
  • Cable: 6mm² SWA
  • Length: 40m to garage
  • Load: 32A continuous

Initial Calculation (6mm²):

mV/A/m for 6mm² SWA = 7.3 mV/A/m (Table 4D4A)

Vd = (7.3 × 40 × 32) ÷ 1000 = 9.344V

Percentage = (9.344 ÷ 230) × 100 = 4.06%

Upgrade to 10mm²:

mV/A/m for 10mm² SWA = 4.4 mV/A/m

Vd = (4.4 × 40 × 32) ÷ 1000 = 5.632V

Percentage = (5.632 ÷ 230) × 100 = 2.45%

✓ Solution: Upgrade to 10mm² SWA for 2.45% voltage drop

Note: 6mm² would work for runs under 28m at 32A

💡 Voltage Drop Calculation Tips

  • Always check before installation - voltage drop often requires larger cables than current capacity
  • Lighting circuits are stricter - 3% limit instead of 5%
  • For long runs, increase cable size to reduce voltage drop
  • Use the calculator above for quick verification of your calculations
  • Remember: One-way length, not return distance

3-Phase Voltage Drop Calculator UK — Formula and Worked Examples

Three-phase voltage drop calculations follow BS 7671 Appendix 4 Section 6, but use a √3 factor and a distinct 3-phase mV/A/m column. This section covers the formula, how 3-phase compares to single-phase for the same cable, and a full worked example for a typical UK commercial sub-main. For full 3-phase cable sizing (including motor FLCs, starting-current considerations, and 4-core SWA derating tables), use the 3-Phase Cable Size Calculator.

3-Phase Voltage Drop Formula (Line-to-Line)

Vd = (mV/A/m × L × IL × √3) ÷ 1000

Variables:

  • mV/A/m — from 3-phase column of Table 4D4B / 4E4B / 4D5
  • L — cable length in metres (one-way)
  • IL — line current (balanced load)
  • √3 ≈ 1.732 (phase-to-line relationship)

Convert to % of 400V line-to-line:

% drop = (Vd ÷ 400) × 100

BS 7671 limits: 3% lighting (12V), 5% other (20V) on 400V systems.

Why 3-Phase Halves Voltage Drop (for the same cable and load)

A 22kW load on single-phase 230V draws 95.7A; the same 22kW balanced across three phases draws only 31.8A per phase. Because voltage drop is proportional to current, spreading the load cuts drop dramatically — even after applying the √3 factor. This is why industrial and commercial installations are almost always 3-phase over any distance.

ScenarioCurrentCableVd over 40mAs % of Vnom
22kW single-phase, 230V95.7A16mm² T&E10.7V4.66%
22kW 3-phase, 400V (balanced)31.8A/phase6mm² 4-core SWA14.1V3.52%

The 3-phase cable is also a third of the single-phase cross-section. Copper cost is lower, cable weight is lower, and the 30mA RCD sizing is easier.

Worked Example: 63A 3-Phase Sub-Main to Factory Unit

Scenario:

  • Load: 63A per phase TP&N sub-main, 400V, PF=0.9
  • Cable: 16mm² 4-core SWA, clipped to cable tray
  • Length: 55m from main LV panel to sub-DB
  • Voltage-drop budget: 2% on sub-main (leaving 3% for final circuits)

Step 1 — Identify mV/A/m (3-phase):

16mm² 4-core SWA, 3-phase column (Table 4D4B) = 2.4 mV/A/m

Step 2 — Apply formula:

Vd = (2.4 × 55 × 63 × √3) ÷ 1000 = 14.41V

Step 3 — Convert to percentage of 400V:

(14.41 ÷ 400) × 100 = 3.60%

Step 4 — Check against budget:

✗ Fails the 2% sub-main budget — upsize to 25mm² 4-core SWA.

Step 5 — Recalculate with 25mm²:

25mm² 4-core SWA 3-phase mV/A/m = 1.5

Vd = (1.5 × 55 × 63 × √3) ÷ 1000 = 9.00V

As % of 400V = 2.25% — still slightly over. Try 35mm²:

35mm² mV/A/m = 1.10; Vd = (1.10 × 55 × 63 × √3) ÷ 1000 = 6.60V = 1.65%

✓ Final answer:

Use 35mm² 4-core SWA for 1.65% drop on the sub-main, leaving 3.35% headroom for final circuits in the sub-DB. Protective device: 63A 3-pole MCCB or BS 88-3 fuse.

SWA Cable Voltage Drop — UK Reference & Long-Run Guidance

Steel wire armoured (SWA) cable is the default for UK outdoor and underground runs — outbuildings, garages, EV chargers, sub-mains and industrial circuits. Its voltage drop values are essentially identical to same-size copper PVC cables because the armour carries no phase current, but several SWA-specific factors affect real-world voltage drop calculations.

SWA mV/A/m Values (Single-Phase & 3-Phase)

Size2-core (1φ)3-core (1φ)4-core (3φ)Typical application
2.5mm²181815Garden lighting, small outbuildings
4.0mm²11119.5Garage sub-mains, small workshops
6.0mm²7.37.36.47kW EV chargers, hot tubs, 22kW 3φ EV
10mm²4.44.43.8Long EV runs, larger outbuildings
16mm²2.82.82.4Commercial sub-mains, workshop feeds
25mm²1.751.751.50100A TP&N sub-mains
35mm²1.251.251.10Long-distance 3φ sub-mains

Values for 70°C PVC-insulated SWA cables reproduced from BS 7671:2018 Table 4D4B. BS 7671 publishes two voltage-drop columns: two-core single-phase AC and three-/ four-core three-phase AC. For a 3-core SWA used on a single-phase circuit (L/N/E) the accepted industry convention is to use the two-core single-phase value shown here — the extra core carries no current. 90°C XLPE SWA (BS 6724 / Table 4E4B) values are within 3% of these figures at design temperature. For 25mm² and above, the tabulated z is the total complex impedance (resistance + reactance).

Worked Example: Long-Run SWA to Outbuilding (7.4kW EV + Lighting)

Scenario:

  • Load: 40A total (32A EV charger + 8A for lighting/sockets diversity)
  • Cable: 2-core SWA buried direct 600mm
  • Length: 65m from CU to detached garage consumer unit
  • Voltage-drop target: ≤ 3% (tight, to protect EV charger PEN-detection algorithms)

Try 10mm² 2-core SWA:

Vd = (4.4 × 65 × 40) ÷ 1000 = 11.44V = 4.97% ✗ (over 3% target)

Try 16mm² 2-core SWA:

Vd = (2.8 × 65 × 40) ÷ 1000 = 7.28V = 3.17% ✗ (still just over)

Try 25mm² 2-core SWA:

Vd = (1.75 × 65 × 40) ÷ 1000 = 4.55V = 1.98%

✓ Final answer:

Use 25mm² 2-core SWA for 1.98% drop. Over 65m, the copper cost difference between 10mm² and 25mm² is significant (~£200 extra) but saves a site visit if the EV charger rejects the installation due to voltage fluctuation. For 3-phase (22kW charger): 10mm² 4-core SWA delivers ~2.1% drop over the same run — a much cheaper option.

SWA-Specific Voltage-Drop Gotchas

  • Armour as CPC is fine for voltage drop but a concern for Zs. The steel armour carries fault current, not phase current, so it doesn't affect voltage drop. However, SWA's armour has a higher resistance per metre than the phase conductor, so long runs may need a separate CPC for earth fault loop impedance compliance.
  • Buried-direct runs stay cooler — voltage drop is usually lower than tabulated. BS 7671 mV/A/m values assume 70°C conductor. Buried cables often operate at 40–50°C in UK soil, reducing conductor resistance by ~10%. Worst-case calculation is still safer for design.
  • 3-core SWA single-phase vs 4-core SWA 3-phase — different columns. A 3-core SWA used single-phase (L/N/earth) uses the single-phase mV/A/m column; a 4-core SWA on balanced 3-phase uses the lower 3-phase column. Don't mix them.
  • Neutral conductor loading on 3-phase 4-wire SWA. Harmonic-rich loads (LED banks, VSD drives) can push neutral current above phase current — affecting both voltage drop and cable heating. See BS 7671 Appendix 4 §11.

How to Fix Excessive Voltage Drop — 5 Remediation Strategies

When a voltage drop calculation exceeds BS 7671 limits (or your design target), upsizing the cable is the default fix — but it isn't always the cheapest or cleverest option. These are the five remediation strategies UK electricians use in practice, ranked roughly from simplest to most involved.

1Upsize the Cable (one or two sizes)

The default fix. Moving from 6mm² to 10mm² roughly halves voltage drop (4.4 → 7.3 mV/A/m — approximately 60% reduction). Typical extra cost: £2–6/m for the extra copper. Works best when the run isn't already at the maximum cable size the terminals will accept (2.5mm² at socket terminals, 10–16mm² at MCB terminals).

When to use: short-to-medium runs (≤30m) with straightforward upsize path. The calculator above automatically suggests the smallest compliant size.

2Shorten the Cable Route

Voltage drop is directly proportional to length. A 20% shorter route = 20% less drop. On long runs with unnecessary detours (over, around and back through loft spaces), re-routing can solve marginal cases for free. Also consider running cables through floors instead of around them, or using external wall routes where compliant.

When to use: new builds and rewires where cable routes are not yet fixed. Rarely viable on retrofit unless major building works are planned.

3Reposition the Distribution Board

If most circuits are long because the consumer unit is tucked in a corner cupboard, relocating the CU closer to the load centre (e.g. central utility room instead of far-corner garage) can reduce average run length by 30–50%. Typical cost: £200–500 plus meter-tail extension. Applies disproportionately to older bungalows and 1970s-plan semis where the CU ended up next to the incoming service head for convenience.

When to use: major refurbishments, CU upgrades, or fuse-board replacements where tails are being replaced anyway.

4Add a Sub-Distribution Board

For large installations (multi-unit residential, commercial, outbuildings, barns), a heavy sub-main to a second DB at the load centre is often cheaper than oversizing every final circuit. Run a 25mm² SWA sub-main to the new DB, then short 2.5mm² and 6mm² final circuits locally. Key Regulation 433.2.2: each DB must have its own overcurrent protection at origin.

When to use: outbuildings, upstairs extensions, garages with heavy loads. The classic UK application is a 40m+ run to a workshop or granny annexe.

5Split the Load Across Multiple Circuits

If one 32A circuit is failing voltage drop at 40m, two 20A radial circuits at the same length and cable size will easily comply — each carries less current, and voltage drop is proportional to current. Especially useful for kitchen circuits (split high-current appliances across two 20A radials), long outbuilding circuits, and EV chargers where a second dedicated circuit can future-proof the installation.

When to use: heavily-loaded kitchens, outbuildings with mixed loads, and when the CU has spare ways. Less practical when CU is already full.

Decision rule of thumb

If the run is under 30m and one cable size bigger fixes the calculation — upsize. If the run is over 50m and you need to go up three cable sizes — split to two circuits or add a sub-main. If the whole installation has long runs — relocate the distribution board. Voltage drop is a design problem, not just a cable-size problem.

Voltage Drop Budget Table — Cumulative Drop From Origin to Load

BS 7671 Appendix 12 specifies voltage drop from the origin of the installation (the DNO cutout or private supply origin) to the final point of use — not per circuit. Real installations use multiple voltage-drop stages. A thoughtful budget allocates the 5% allowance across those stages so no one stage consumes the entire headroom.

Typical UK Installation Budgets

Installation TypeTailsSub-mainFinal circuitTotal (max)
Small domestic (single CU)~0.5%≤4.5%5% (power)
Domestic + outbuilding DB~0.5%≤2%≤2.5%5% (power)
Small commercial (meter → DB → finals)~0.5%≤1.5%≤3%5% (power)
Commercial lighting (to furthest fitting)~0.5%≤1%≤1.5%3% (lighting)
Industrial 3-phase (main panel → sub-DB → motor)≤1.5%≤3.5%5% (power)
Private LV supply (site generator, large solar)up to 1%up to 3%up to 4%8% (private)

Energy Cost of Voltage Drop — Power Loss is Quadratic

Voltage drop isn't a cosmetic number — it's real power dissipated as cable heat, governed by Ploss = I²R. At 5% drop, roughly 5% of delivered power is wasted in the cable. For heavily-loaded commercial circuits, the energy cost of undersized cables can justify upsizing within a few years.

CircuitLoad hours/yrVdEst. cable energy loss (£/yr at 30p/kWh)
Domestic ring final, 20A typical~500h3%~£0.70
Commercial office lighting, 30A~3,000h3%~£21
Industrial 100A 3φ sub-main~4,000h5%~£400
Data centre 3φ sub-main, 300A continuous~8,760h5%~£7,800

Estimates assume balanced resistive load and average 30p/kWh commercial electricity. Regulation 132.5 and BS 7671 Appendix 17 encourage design below the 5% ceiling specifically to reduce this energy waste. Upsizing one cable step often pays back in under 5 years on high-duty-cycle circuits.

Design rule: always verify voltage drop at the furthest point of use, not just at the sub-DB input. For lighting circuits the stricter 3% limit applies — so commercial lighting designs often run finals in 1.5mm² instead of 1.0mm² specifically to keep cumulative drop under 3%.

Advanced Voltage Drop Considerations - UK Regulations

Professional electricians need to understand these advanced concepts for complex installations and edge cases that affect voltage drop compliance.

ESQCR Supply Voltage Limits - The Real Starting Point

The Electricity Safety, Quality and Continuity Regulations (ESQCR) 2002 define UK supply voltage limits that affect how you budget voltage drop.

NominalToleranceRange
230V+10% / -6%216.2V to 253V
400V (3-phase)+10% / -6%376V to 440V

The Critical Insight: If supply arrives at 216.2V (minimum allowed), a 5% installation drop leaves only 205.4V at the load. Many appliances specify minimum 207V operation. For critical loads, aim for 3-4% total drop, not 5%.

Cumulative Voltage Drop - Sub-Main + Final Circuit

BS 7671 limits apply to total voltage drop from origin to load, not just the final circuit. For installations with sub-distribution boards, you must budget carefully.

Voltage Drop Budget Example:

Total allowed: 5% (11.5V)

Sub-main (meter to DB): 1.5% (3.45V)

Final circuit (DB to socket): 3.5% (8.05V)

Total: 5.0% ✓ Compliant

Common Mistake: Calculating final circuit drop without checking what drop already exists on the sub-main. A 40m sub-main at 100A on 25mm² cable already uses 2.1% of your budget.

Understanding mV/A/m - Resistance vs Impedance

The mV/A/m values in BS 7671 tables account for more than just conductor resistance. They include the complex impedance at operating temperature.

What mV/A/m Includes:

  • • Conductor DC resistance at 70°C (PVC) or 90°C (XLPE)
  • • Skin effect (significant above 120mm²)
  • • Proximity effect in grouped cables
  • • Inductive reactance (XL)

Temperature Correction:

  • • Tables assume conductor at max operating temperature
  • • Actual drop may be lower if cable runs cool
  • • For lightly loaded cables, actual drop could be 80-90% of calculated

For precise design calculations, BS 7671 Appendix 4 provides separate r (resistance) and x (reactance) components for complex impedance calculations.

Motor Starting Voltage Drop - The 6-8× Factor

Induction motors draw 6-8 times Full Load Current (FLC) during Direct-On-Line (DOL) starting. This causes temporary voltage drop that can affect starting performance.

Running VdStarting Vd (×7)Impact
2%14%Acceptable
3%21%Marginal
5%35%May stall

Rule of Thumb: For motors, limit running voltage drop to 2-3% so starting drop stays under 20%. Use soft starters or VFDs for long cable runs.

Power Factor and Reactive Loads

For resistive loads (heaters, kettles), the simple mV/A/m calculation is accurate. For inductive loads (motors, transformers), power factor affects both current and voltage drop characteristics.

Impact on Design:

  • • Low PF loads draw more current for same kW
  • • A 10kW motor at 0.8 PF draws 54.3A (not 43.5A as pure resistive)
  • • Higher current = proportionally higher voltage drop
  • • BS 7671 mV/A/m values assume unity PF for resistive loads

For accurate motor circuit design: Use the actual current (Watts ÷ Volts ÷ PF) not the theoretical resistive current, when calculating voltage drop.

EV Charger Voltage Drop - Real World Considerations

EV chargers present unique voltage drop challenges because they operate at high current for extended periods, often at the end of long cable runs.

7.4kW Charger (32A)

  • Up to 25m: 6mm² SWA (3.2% drop)
  • 25-50m: 10mm² SWA (2.8% drop)
  • 50m+: Consider 16mm² or voltage boost

22kW Charger (32A 3-phase)

  • Up to 40m: 6mm² 4-core SWA
  • 40-80m: 10mm² 4-core SWA
  • Lower voltage drop per phase (√3 factor)

OZEV grant regulations require voltage drop compliance certification. Oversizing cable avoids costly corrections and future-proofs for higher-power chargers.

Electric Shower Voltage Drop - Why It Matters More

Electric showers are particularly sensitive to voltage drop because the heating element output is proportional to V². A 5% voltage drop causes approximately 10% reduction in heating power.

Power Reduction Example (9.5kW shower):

At 230V:

9.5kW output

At 218.5V (5% drop):

8.55kW output (-10%)

At 210V (8.7% drop):

7.9kW output (-17%)

Recommendation: For electric showers, aim for maximum 3% voltage drop to maintain adequate hot water temperature, especially in winter.

Professional Best Practice

When designing circuits, consider voltage drop early in the process:

  • Calculate voltage drop before selecting cable size for current capacity
  • Budget sub-main drop before designing final circuits
  • Use 3% as a practical target, saving margin for supply variations
  • Document voltage drop calculations on design records for compliance

How to Use the Voltage Drop Calculator

Use this calculator to verify that your cable installation meets BS 7671 voltage drop requirements before energizing the circuit.

  1. Enter the load current - The actual current (in Amps) flowing through the cable under normal operation.
  2. Specify the cable length - The one-way distance (in meters) from the distribution board to the load point.
  3. Select the cable size - The cross-sectional area of the conductor in mm² (e.g., 2.5mm², 4.0mm², etc.).
  4. Choose the voltage - 230V for single-phase or 400V for three-phase installations.
  5. Select conductor material - Copper is standard in the UK. Aluminium has higher resistance.

Understanding Voltage Drop

Voltage drop is the reduction in voltage that occurs as electrical current flows through a conductor due to the conductor's resistance. Excessive voltage drop can cause:

  • Poor performance of electrical equipment
  • Dimming of lights
  • Overheating of motors
  • Reduced equipment lifespan

BS 7671 Limits

  • Lighting circuits: Maximum 3% voltage drop
  • Other circuits: Maximum 5% voltage drop

BS 7671 Regulation 525 - Voltage Drop

This calculator checks compliance with BS 7671:2018+A2:2022 Regulation 525 - Voltage drop in consumers' installations.

Regulation 525.1

Under normal service conditions, the voltage drop between the origin of the installation (usually the supply terminals of the consumer unit) and any socket outlet or other point of utilization shall not exceed the values given in Appendix 12:

  • 3% for lighting circuits - To prevent visible dimming
  • 5% for other uses - Power circuits, heating, etc.

How Voltage Drop is Calculated

The calculator uses the following formula:

Single-phase: Vdrop = 2 × I × L × R
Three-phase: Vdrop = √3 × I × L × R

Where: I = Current (A), L = Length (m), R = Resistance (Ω/m)

Note: Voltage drop is only one consideration. Cable selection must also account for current-carrying capacity, overcurrent protection, and fault protection requirements.

Frequently Asked Questions

Free: BS 7671 Quick Reference Card

Max Zs values, diversity factors, cable ratings, voltage drop — one printable page. Plus occasional emails with calculator updates and useful tips.

Was this calculation helpful?

Complete Calculation Workflow

Follow this workflow for a complete electrical installation calculation: